Commercial Projects

...

St Augustine Catholic School

Toronto, ON

This intricate project consisted of many components. Everything had to be carefully planned out, & attention to detail was key. We built a raised playground, graded & sodded all the areas around the school, planted & caged over 100 trees, & installed engineered silva cell 2 systems for trees in concrete areas. The playground was built up by constructing a Unilock Pisa Block retaining wall with a geogrid system. The entire area inside the playground was backfilled and compacted in increments. Weeping tile drainage system was installed & connected to the catch basin. Compaction testing was arranged. Cedar log sand play areas were built. All the woodwork was planes & sanded to achieve a high quality & uniform finish. A concrete slab was poured. 3 permeable artificial turf areas were installed. A metal fence was installed along the perimeter. Many areas inside the playground and along the retaining wall were landscaped.

St Augustine Catholic School 1
St Augustine Catholic School 2
St Augustine Catholic School 3
St Augustine Catholic School 4
St Augustine Catholic School 5

Aaniin Community Centre

Markham, Ontario

This intricate stone project involved the installation of etched granite for a water feature. There were no additional slabs & every slab had a unique pattern that flows through to the next slab. Areas with water jets & lights had to be carefully core-drilled. The accuracy limit had to stay within 1/8”. A polymer re-inforced cement was used to bond the pieces. A water resistant grout was used to grout the joints once the granite was in place.

Aaniin Community Centre 1
Aaniin Community Centre 2
Aaniin Community Centre 3
Aaniin Community Centre 4

City of Toronto Boulevard Restoration

Toronto, Ontario

This civil project consisted of new power lines & utilities being installed. The nature of the project is invasive & the objective is to remediate the damage asap and provide good customer service. All trenched areas were backfilled with fresh topsoil & edged so that the new sod meets the existing lawn nicely. New sod was installed and watered for 2 weeks to achieve proper rooting. Areas with interlocking stone were dismantled and re-assembled as soon as the trench work was complete. Interlocking stone was compacted thoroughly & jointed with polymeric sand so that the new stonework does not settle. After the paver installation was complete & the grass grew in, you could not even tell the work had taken place.

Aaniin Community Centre 1
Aaniin Community Centre 2
Aaniin Community Centre 3
Aaniin Community Centre 4
Aaniin Community Centre 4

*Fully Insured and Bonded*